Current Project: Remodel The Cabins |
Sub-Project: Cabin Addition |
|
Goal: Add an Addition that joins our Sycamore & Walnut cabins together.
Completion Rate: 90% Description: We have begun a 250 Sq. Ft. Addition that joins our Sycamore & Walnut cabins together. It will hold a bathroom + shower, kitchenette, laundry, and sitting area. In the Fall of 2024, we poured concrete and built a "cold shell" with roofing, siding, windows, and doors. In the early Winter of 2026, we were able to drywall, mud, and install a mini-split. In the Spring of 2026, major progress was made to finish out the interior, except for the bathroom + shower. The project is funded up to this point: Benefit: This will add an appealing spot for rental groups, and it will be nice for campers and guests to not have to go outside at night to get to the bathroom! Further Need: $1000 in funding and/or donated items including; Pouring paint-fleck epoxy in the bathroom and installing grab bars and a toilet paper holder. |
|